Projects

Fort Smith Retail Center

On Track

Beckham Construction Group · Fort Smith, AR

Managed Material Budget

$412,000

Procurement Progress

94%

Construction Start

Apr 14, 2026

Expected Completion

Jan 30, 2027

Project Summary

Project Address

1450 Towson Ave

City / State / ZIP

Fort Smith, AR 72901

Project Type

Commercial

BuilderSpec Service

Contractor Provided Material List

Material Scope

RoofingLumber / FramingElectricalHVAC

Budget

Approved Material Budget$412,000
Current Estimated Cost$418,900
Authorized Procurement$105,810
Ordered / Committed$105,810
Remaining Budget$306,190
Variance$6,900

Approval Status

  • Project Scope & AuthorizationApproved
  • Material Scope ApprovalApproved
  • Procurement ApprovalApproved

Upcoming Milestones

  • Roofing package delivery

    Aug 12

    Complete
  • Framing inspection

    Oct 21

    Upcoming
  • HVAC rough-in complete

    Nov 3

    Upcoming

Project Exceptions

  • Upcoming Order Deadline

    HVAC rough-in materials must be ordered by Sep 10 to hold schedule.

  • Substitution Proposed

    Ozark Roofing Wholesale proposed a substituted ridge vent product on their quote for Roofing Package.