Fort Smith Retail Center

Framing Package

Draft

Beckham Construction Group · Lumber / Framing · Contractor Provided

Estimated Value

$86,500

Item Count

3

Required On Site

Sep 15, 2026

Current Revision

Revision 1

Material Approval

Revision 1 · Last updated Aug 20, 2026

Draft

Material Schedule

3 line items

Item / MaterialCategoryManufacturer / ModelSpecificationQtyUOMRequired On SiteSource of Qty

2x6 Kiln-Dried Lumber

Wall framing

Lumber / Framing—SPF #23,200LFSep 15, 2026Contractor Provided

LVL Beams

Structural headers

Lumber / FramingWeyerhaeuser / TimberStrand1.75" x 11.875"36EASep 15, 2026Contractor Provided

Sheathing Plywood

Wall and roof sheathing

Lumber / Framing—7/16" OSB640SheetsSep 15, 2026Contractor Provided

Revision History

  • Revision 1Current
    Not Submitted

    Created Aug 20, 2026 by Michael Varner

    Initial working list from contractor takeoff.