Procurement — Roofing Package
Beckham Construction Group · $105,810 from Summit Roofing Supply
CONTRACTOR APPROVAL REQUIRED
Current approved material revision
Quote references the current approved revision.
Within approved scope
Material package is approved / ready for sourcing.
Within remaining authorized budget
$105,810 purchase within remaining authorized budget of $128,000.
Within procurement authority
Exceeds the $25,000 procurement authorization threshold.
No unapproved substitutions
All quoted line items meet specification.
BuilderSpec authorized to place orders
Standing purchasing authorization is in effect for this project.
Exceptions Requiring Approval
- • Above Procurement Authorization Threshold: Purchase amount $105,810 exceeds the procurement authorization threshold of $25,000.
Procurement Status
Last updated Jul 6, 2026
AUTHORIZED FOR PURCHASE
Purchase Order BS-2026-0003
Created Jul 7, 2026
Material Scope
Material Package
Roofing Package →Category
Roofing
Approved Revision
Revision 1
Approved By
Dana Beckham
Approval Date
May 6, 2026
Required On Site
Aug 14, 2026
Budget
Estimated Material Value ($128,000) is shown for reference only — it is never treated as authorized purchasing budget.
Recommended Source
Vendor
Summit Roofing Supply →Quote Number
SRS-Q-3391
Quote Amount
$105,810
Freight
$0
Expected Delivery
Aug 5, 2026
Lead Time
1-2 weeks
Availability
In Stock
Specification Compliance
Compliant
Recommendation Reason
Ozark Roofing Wholesale is $4,520 lower, but their expected delivery (Aug 19) is 5 days after the required-on-site date (Aug 14) and proposes a substituted ridge vent product. Summit Roofing Supply meets the required schedule with no substitutions, and BuilderSpec already holds an authorized purchasing account with them.
BUILDERSPEC
Construction Procurement & Material Management
Procurement Authorization
Printed November 1, 2026
Contractor
Beckham Construction Group
Project
Fort Smith Retail Center
Fort Smith, AR
Material Package
Roofing Package (Roofing)
Approved Material Revision
Revision 1
Vendor
Summit Roofing Supply
Quote
SRS-Q-3391
| Purchase Amount | $105,810 |
| Approved Material Budget | $128,000 |
| Variance | $22,190 under |
| Authorization Source | Contractor Approval |
| Authorized Date | Jul 6, 2026 |
| Authorized By | Dana Beckham |
Contractor Comments
Approved — please proceed with Summit Roofing Supply.