Roofing Package
ApprovedBeckham Construction Group · Roofing · Contractor Provided
Estimated Value
$128,000
Item Count
4
Required On Site
Aug 14, 2026
Current Revision
Revision 1
Material Approval
Revision 1 · Last updated May 6, 2026
APPROVED MATERIAL BASELINE
Revision 1 approved May 6, 2026 by Dana Beckham. This revision is locked — changes require a new revision.
Sourcing: Ready for Procurement
Material Schedule
4 line items
Revision 1 is locked — create a new revision to change the material schedule.
| Item / Material | Category | Manufacturer / Model | Specification | Qty | UOM | Required On Site | Source of Qty |
|---|---|---|---|---|---|---|---|
Architectural Shingles 30-year architectural shingles | Roofing | GAF / Timberline HDZ | Charcoal | 420 | Bundles | Aug 14, 2026 | Contractor Provided |
Synthetic Underlayment Synthetic roofing underlayment | Roofing | GAF / FeltBuster | — | 40 | Rolls | Aug 14, 2026 | Contractor Provided |
Ridge Vent | Roofing | GAF / Cobra Rigid Vent 3 | — | 180 | LF | Aug 14, 2026 | Contractor Provided |
Drip Edge | Roofing | — | Aluminum, mill finish | 900 | LF | Aug 14, 2026 | Contractor Provided |
Revision History
- Revision 1CurrentApproved
Created Apr 22, 2026 by Dana Beckham
Initial contractor-provided material list.
Submitted for approval Apr 22, 2026
Approved May 6, 2026 by Dana Beckham
BUILDERSPEC
Construction Procurement & Material Management
Material Schedule
Printed November 1, 2026
Project
Fort Smith Retail Center
Fort Smith, AR
Contractor
Beckham Construction Group
Package
Roofing Package (Roofing)
Revision
Revision 1
Approval Status
Approved
Approved
May 6, 2026 by Dana Beckham
Required On Site
Aug 14, 2026
Estimated Value
$128,000
| Item | Manufacturer / Model | Specification | Qty | UOM | Required On Site | Source |
|---|---|---|---|---|---|---|
| Architectural Shingles | GAF / Timberline HDZ | Charcoal | 420 | Bundles | Aug 14, 2026 | Contractor Provided |
| Synthetic Underlayment | GAF / FeltBuster | — | 40 | Rolls | Aug 14, 2026 | Contractor Provided |
| Ridge Vent | GAF / Cobra Rigid Vent 3 | — | 180 | LF | Aug 14, 2026 | Contractor Provided |
| Drip Edge | — | Aluminum, mill finish | 900 | LF | Aug 14, 2026 | Contractor Provided |