| Project | Customer | Material Package | Recommended Vendor | Recommended Amount | Approved Budget | Variance | Procurement Authority | Current Status |
|---|---|---|---|---|---|---|---|---|
| Fort Smith Retail Center | Beckham Construction Group | Roofing Package | Summit Roofing Supply | $105,810 | $128,000 | $22,190 | Contractor Approval Required | Authorized for Purchase |
| Northgate Distribution Facility | Ridgeline Contractors | Concrete & Masonry Package | Northgate Building Materials | $250,950 | $244,000 | -$6,950 | Contractor Approval Required | Authorized for Purchase |
| Commerce Park Building B | Beckham Construction Group | Hardware Package | Heritage Millwork | $8,430 | $9,000 | $570 | Contractor Approval Required | Awaiting Contractor Approval |