Projects

Commerce Park Building B

Re-Authorization Required

Beckham Construction Group · Fort Smith, AR

Managed Material Budget

$521,000

Procurement Progress

34%

Construction Start

Jun 16, 2026

Expected Completion

Apr 8, 2027

Project Summary

Project Address

500 Commerce Park Dr

City / State / ZIP

Fort Smith, AR 72916

Project Type

Commercial

BuilderSpec Service

Contractor Provided Material List

Material Scope

PlumbingConcrete / MasonryCabinets / Countertops

Budget

Approved Material Budget$521,000
Current Estimated Cost$507,300
Authorized Procurement$0
Ordered / Committed$0
Remaining Budget$521,000
Variance-$13,700

Approval Status

  • Project Scope & AuthorizationApproved
  • Material Scope ApprovalApproved
  • Procurement ApprovalPending

Upcoming Milestones

  • Concrete order placed

    Sep 12

    Upcoming

Project Exceptions

  • Contractor Approval Required

    Hardware Package purchasing is blocked until Dana Beckham re-authorizes the $9,115 confirmed amount against the $9,000 approved budget — requested Aug 25.