Procurement — Hardware Package
Beckham Construction Group · $9,115 from Heritage Millwork
CONTRACTOR APPROVAL REQUIRED
Current approved material revision
Quote references the current approved revision.
Within approved scope
Material package is approved / ready for sourcing.
Within remaining authorized budget
$9,115 purchase exceeds remaining authorized budget of $9,000 by $115.
Within procurement authority
Within the $25,000 procurement authorization threshold.
No unapproved substitutions
All quoted line items meet specification.
BuilderSpec authorized to place orders
Standing purchasing authorization is in effect for this project.
Exceptions Requiring Approval
- • Over Approved Budget: Recommended purchase exceeds the remaining authorized budget by $115.
- • Other: Reset from Authorized for Purchase on Aug 24 — Heritage Millwork's acknowledgment confirmed $9,115 against the $9,000 approved material budget (+$115) and proposed an unreviewed National Hinge Co. substitution for the specified Hager BB1279 hinges. Re-authorization requested from Dana Beckham on Aug 25; no purchasing may proceed until she responds.
Procurement Status
Last updated Aug 25, 2026
Purchase Order BS-2026-0002
Created Aug 18, 2026
Material Scope
Material Package
Hardware Package →Category
Hardware
Approved Revision
Revision 1
Approved By
Dana Beckham
Approval Date
Aug 12, 2026
Required On Site
Oct 1, 2026
Budget
Estimated Material Value ($9,000) is shown for reference only — it is never treated as authorized purchasing budget.
Recommended Source
Vendor
Heritage Millwork →Quote Number
HM-Q-2201
Quote Amount
$8,430
Freight
$150
Expected Delivery
Sep 20, 2026
Lead Time
4-6 weeks
Availability
In Stock
Specification Compliance
Compliant
Recommendation Reason
Only vendor quoted for this package; pricing and availability are acceptable and well within budget.
BUILDERSPEC
Construction Procurement & Material Management
Procurement Authorization
Printed November 1, 2026
Contractor
Beckham Construction Group
Project
Commerce Park Building B
Fort Smith, AR
Material Package
Hardware Package (Hardware)
Approved Material Revision
Revision 1
Vendor
Heritage Millwork
Quote
HM-Q-2201
| Purchase Amount | $8,430 |
| Approved Material Budget | $9,000 |
| Variance | $570 under |
| Authorization Source | Contractor Approval |
| Authorized Date | |
| Authorized By |