Sourcing — Hardware Package
Ready for ProcurementBeckham Construction Group · Hardware
Estimated Material Value
$9,000
Vendors Requested
1
Quotes Received
1
Required On Site
Oct 1, 2026
Material Schedule Being Quoted
Approved Revision 1 — this is the exact scope vendors are pricing.
| Material | Specification | Quantity | Unit | Required On Site |
|---|---|---|---|---|
| Door Hinges | 4.5" x 4.5", satin chrome | 180 | EA | Oct 1, 2026 |
| Lever Handle Sets | Satin chrome | 60 | EA | Oct 1, 2026 |
| Door Closers | — | 24 | EA | Oct 1, 2026 |
Select Vendors
Vendors that supply Hardware, matched against this project's contractor relationships.
- Anderson Hardware Distributors
Northwest Arkansas · Lead time 1 week · Reliability: poor
Connected Supplier Pricing
Demo Connected PricingQueries the connected supplier accounts on file for this material package and returns current price, availability and lead time per line — without sending an RFQ. Results below are informational until you add one as a quote.
Pricing for Commerce Park Building B · Customer supplier account
Simulated supplier responses for demonstration purposes. Production connections may provide account-specific pricing and availability where supported.
No pricing checked yet. Run a check to compare current supplier price, availability and lead time side by side.
Requests for Quote
For V1 this is a tracking workflow only — no real email is sent.
Heritage Millwork
Quote ReceivedLinda Marsh · Requested Aug 13, 2026 · Due Aug 17, 2026
Quote entered — see comparison below.
Quote Comparison
Lowest price is shown for reference only — it is not an automatic recommendation.
| Vendor | Heritage Millwork Lowest Price |
|---|---|
| Total Price | $8,430 |
| Material / Subtotal | $8,280 |
| Freight | $150 |
| Other Charges | $0 |
| Availability | In Stock |
| Lead Time | 4-6 weeks |
| Expected Delivery | Sep 20, 2026 |
| Required On Site (Oct 1, 2026) | On Schedule |
| Specification Compliance | Compliant |
| Quote Expiration | Sep 15, 2026 |
| Contractor Account | Authorized |
| Vendor Reliability | Good |
Sourcing Recommendation
Ready for ProcurementRecommended Vendor
Heritage Millwork
Recommended Quote Total
$8,430
Required On Site
Oct 1, 2026
Expected Delivery
Sep 20, 2026
Quote vs. Estimate
The estimate is a planning figure, not an authorized purchasing budget — the budget test is applied when this package reaches procurement authorization.
Recommendation Reason
Only vendor quoted for this package; pricing and availability are acceptable and well within budget.
Decided by Michael Varner on Aug 17, 2026
BUILDERSPEC
Construction Procurement & Material Management
Quote Comparison
Printed November 1, 2026
Project
Commerce Park Building B
Fort Smith, AR
Contractor
Beckham Construction Group
Material Package
Hardware Package (Hardware)
Approved Revision
Revision 1
| Vendor | Total Quote | Freight | Lead Time | Expected Delivery | Availability | Spec Compliance |
|---|---|---|---|---|---|---|
| Heritage Millwork | $8,430 | $150 | 4-6 weeks | Sep 20, 2026 | In Stock | Compliant |
Recommended Vendor: Heritage Millwork
Only vendor quoted for this package; pricing and availability are acceptable and well within budget.
Decided by Michael Varner on Aug 17, 2026