BUILDERSPEC
Construction Procurement & Material Management
Material Scope Review
Fort Smith Retail Center · Fort Smith, AR
Contractor
Beckham Construction Group
Revision
Revision 1
Required On Site
Aug 14, 2026
Estimated Value
$128,000
| Item | Specification | Qty | UOM | Required On Site |
|---|---|---|---|---|
Architectural Shingles 30-year architectural shingles | GAF — Timberline HDZ — Charcoal | 420 | Bundles | Aug 14, 2026 |
Synthetic Underlayment Synthetic roofing underlayment | GAF — FeltBuster | 40 | Rolls | Aug 14, 2026 |
Ridge Vent | GAF — Cobra Rigid Vent 3 | 180 | LF | Aug 14, 2026 |
Drip Edge | Aluminum, mill finish | 900 | LF | Aug 14, 2026 |
You approved this revision on May 6, 2026. BuilderSpec will proceed with sourcing against this material scope.