Procurement Approval Request

Hardware Package

Commerce Park Building B ยท Fort Smith, AR

Vendor

Heritage Millwork

Material Revision

Revision 1

Purchase Amount

$9,115

Required On Site

Oct 1, 2026

Budget

Budget: $9,000Variance: -$115

Reason Approval Is Required

Sent to Dana Beckham for re-authorization: Heritage Millwork confirmed $9,115 against the $9,000 approved material budget (+$115) and proposed an unreviewed National Hinge Co. substitution for the specified Hager BB1279 hinges.

By approving, you authorize BuilderSpec to proceed with this purchase from Heritage Millwork at $9,115 against Revision 1 of Hardware Package.