Sourcing — Concrete & Masonry Package
Ready for ProcurementRidgeline Contractors · Concrete / Masonry
Estimated Material Value
$244,000
Vendors Requested
2
Quotes Received
2
Required On Site
Jun 15, 2026
Material Schedule Being Quoted
Approved Revision 1 — this is the exact scope vendors are pricing.
| Material | Specification | Quantity | Unit | Required On Site |
|---|---|---|---|---|
| Ready-Mix Concrete | 4000 PSI | 1,850 | CY | Jun 15, 2026 |
| Rebar, #5 | Grade 60 | 42,000 | LF | Jun 15, 2026 |
| CMU Block | 8" x 8" x 16" | 6,200 | EA | Jun 15, 2026 |
No additional vendors found for Concrete / Masonry in the directory.
Connected Supplier Pricing
Demo Connected PricingQueries the connected supplier accounts on file for this material package and returns current price, availability and lead time per line — without sending an RFQ. Results below are informational until you add one as a quote.
Pricing for Northgate Distribution Facility · Customer supplier account
Simulated supplier responses for demonstration purposes. Production connections may provide account-specific pricing and availability where supported.
No pricing checked yet. Run a check to compare current supplier price, availability and lead time side by side.
Requests for Quote
For V1 this is a tracking workflow only — no real email is sent.
Northgate Building Materials
Quote ReceivedWanda Price · Requested May 26, 2026 · Due Jun 2, 2026
Quote entered — see comparison below.
Regional Concrete Supply
Quote ReceivedCurtis Meyer · Requested May 26, 2026 · Due Jun 2, 2026
Quote entered — see comparison below.
Quote Comparison
Lowest price is shown for reference only — it is not an automatic recommendation.
| Vendor | Northgate Building Materials | Regional Concrete Supply Lowest Price |
|---|---|---|
| Total Price | $250,950 | $227,988 |
| Material / Subtotal | $244,150 | $219,988 |
| Freight | $6,800 | $8,000 |
| Other Charges | $0 | $0 |
| Availability | Available | Limited |
| Lead Time | 2-3 weeks | 3-4 weeks |
| Expected Delivery | Jun 15, 2026 | Jul 1, 2026 |
| Required On Site (Jun 15, 2026) | On Schedule | Schedule Risk |
| Specification Compliance | Substitution Proposed | Compliant |
| Quote Expiration | Jul 1, 2026 (Expired) | Jul 8, 2026 (Expired) |
| Contractor Account | Authorized | No account on file |
| Vendor Reliability | Excellent | Not Rated |
Sourcing Recommendation
Ready for ProcurementRecommended Vendor
Northgate Building Materials
Recommended Quote Total
$250,950
Required On Site
Jun 15, 2026
Expected Delivery
Jun 15, 2026
Quote vs. Estimate
The estimate is a planning figure, not an authorized purchasing budget — the budget test is applied when this package reaches procurement authorization.
Recommendation Reason
Regional Concrete Supply is $22,962 lower, but they are a new vendor with no track record, quoted limited availability, and their expected delivery (Jul 1) is after the required-on-site date (Jun 15). Northgate Building Materials is a known, reliable vendor with an authorized contractor account and meets the required schedule, despite exceeding the package budget.
Decided by Michael Varner on Jun 12, 2026
Substitutions / Exceptions
- • 8x8x16 Lightweight CMU Block (alternate aggregate mix) — Proposed lightweight-aggregate CMU as a comparable alternative to the specified standard-weight block — pending review.
BUILDERSPEC
Construction Procurement & Material Management
Quote Comparison
Printed November 1, 2026
Project
Northgate Distribution Facility
Tulsa, OK
Contractor
Ridgeline Contractors
Material Package
Concrete & Masonry Package (Concrete / Masonry)
Approved Revision
Revision 1
| Vendor | Total Quote | Freight | Lead Time | Expected Delivery | Availability | Spec Compliance |
|---|---|---|---|---|---|---|
| Northgate Building Materials | $250,950 | $6,800 | 2-3 weeks | Jun 15, 2026 | Available | Substitution Proposed |
| Regional Concrete Supply | $227,988 | $8,000 | 3-4 weeks | Jul 1, 2026 | Limited | Compliant |
Recommended Vendor: Northgate Building Materials
Regional Concrete Supply is $22,962 lower, but they are a new vendor with no track record, quoted limited availability, and their expected delivery (Jul 1) is after the required-on-site date (Jun 15). Northgate Building Materials is a known, reliable vendor with an authorized contractor account and meets the required schedule, despite exceeding the package budget.
Decided by Michael Varner on Jun 12, 2026