Procurement — Concrete & Masonry Package
Ridgeline Contractors · $250,950 from Northgate Building Materials
CONTRACTOR APPROVAL REQUIRED
Current approved material revision
Quote references the current approved revision.
Within approved scope
Material package is approved / ready for sourcing.
Within remaining authorized budget
$250,950 purchase exceeds remaining authorized budget of $244,000 by $6,950.
Within procurement authority
Exceeds the $30,000 procurement authorization threshold.
No unapproved substitutions
One or more quote line items propose a substitution or do not meet specification.
BuilderSpec authorized to place orders
Standing purchasing authorization is in effect for this project.
Exceptions Requiring Approval
- • Over Approved Budget: Recommended purchase exceeds the remaining authorized budget by $6,950.
- • Above Procurement Authorization Threshold: Purchase amount $250,950 exceeds the procurement authorization threshold of $30,000.
- • Substitution Requires Approval: The recommended quote includes a proposed substitution or non-compliant item.
Procurement Status
Last updated Jun 13, 2026
AUTHORIZED FOR PURCHASE
Purchase Order BS-2026-0001
Created Jun 14, 2026
Material Scope
Material Package
Concrete & Masonry Package →Category
Concrete / Masonry
Approved Revision
Revision 1
Approved By
Todd Halloran
Approval Date
May 20, 2026
Required On Site
Jun 15, 2026
Budget
Estimated Material Value ($244,000) is shown for reference only — it is never treated as authorized purchasing budget.
Recommended Source
Quote Number
NBM-Q-5510
Quote Amount
$250,950
Freight
$6,800
Expected Delivery
Jun 15, 2026
Lead Time
2-3 weeks
Availability
Available
Specification Compliance
Substitution Proposed
Recommendation Reason
Regional Concrete Supply is $22,962 lower, but they are a new vendor with no track record, quoted limited availability, and their expected delivery (Jul 1) is after the required-on-site date (Jun 15). Northgate Building Materials is a known, reliable vendor with an authorized contractor account and meets the required schedule, despite exceeding the package budget.
BUILDERSPEC
Construction Procurement & Material Management
Procurement Authorization
Printed November 1, 2026
Contractor
Ridgeline Contractors
Project
Northgate Distribution Facility
Tulsa, OK
Material Package
Concrete & Masonry Package (Concrete / Masonry)
Approved Material Revision
Revision 1
Vendor
Northgate Building Materials
Quote
NBM-Q-5510
| Purchase Amount | $250,950 |
| Approved Material Budget | $244,000 |
| Variance | -$6,950 over |
| Authorization Source | Contractor Approval |
| Authorized Date | Jun 13, 2026 |
| Authorized By | Todd Halloran |
Contractor Comments
Approved — schedule reliability is worth the premium. Please proceed with Northgate.
Todd Halloran — Jun 13, 2026