Managed Material Budget
$680,000
Procurement Progress
41%
Construction Start
May 5, 2026
Expected Completion
Mar 12, 2027
Project Summary
Project Address
88 Riverfront Dr
City / State / ZIP
Springdale, AR 72762
Project Type
Commercial
BuilderSpec Service
BuilderSpec Takeoff / Material Calculation
Material Scope
ElectricalPlumbingHVACDrywallFixtures
Budget
Approved Material Budget$680,000
Current Estimated Cost$671,200
Authorized Procurement$0
Ordered / Committed$0
Remaining Budget$680,000
Variance-$8,800
Approval Status
- Project Scope & AuthorizationApproved
- Material Scope ApprovalPending
- Procurement ApprovalNot Required
Upcoming Milestones
- Upcoming
Electrical scope approval
Sep 2
- Upcoming
Plumbing vendor selection
Sep 15
- Upcoming
Drywall material order
Oct 1
Project Exceptions
Contractor Approval Required
Electrical material package awaiting approval from Marcus Underwood.
Material Approval Overdue
Electrical Rough-In (Rev. 1) has been awaiting contractor approval since Aug 26.
Print / Export